Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

733 GW Withdrew from U.S. Interconnection Queues in 2025

By Steven Zhang, and Chris Talley
February 2026

U.S. interconnection queues saw record withdrawals in 2024, but even those record-breaking numbers were eclipsed by the broad purge that occurred in 2025. 733 gigawatts of proposed generation capacity withdrew across 4,061 projects.1

The shotgun approach to queue applications has become prohibitively costly since the widespread implementation of FERC Order 2023. Higher deposits and stricter site control requirements at earlier deadlines were implemented to disincentivize exactly this behavior. And from the 2024 and 2025 data, this approach appears to be working. MISO completed massive study cycles. PJM continued its transition. And across every region, the result was the same: projects that couldn't back up their applications were removed earlier than in previous years.

We're left with a leaner, more serious queue. But queue reform is far from the only factor that drove unexpected behavior in 2025. The One Big Beautiful Bill Act (OBBBA), supply chain constraints, and the era-defining data center buildout all influenced generation queues in unforeseen ways.

1 Our 2024 retrospective counted 296 GW in withdrawals, but that figure only captured projects with explicitly recorded withdrawal dates, an estimated half to two-thirds of actual withdrawals. This year's methodology is more comprehensive (see Methodology section below). Even adjusting for the difference, 2025's total represents a massive escalation.

The Year in Withdrawals

Withdrawals arrived in waves, largely tied to tightly-bound cluster deadlines. December peaked at 131 GW across 775 projects, but every single month of 2025 saw meaningful exits from the queue. Q3 and Q4 saw massive withdrawn capacities. Q3 withdrawals were driven largely by MISO's DPP 2022 cluster (272 withdrawn projects totaling 48.4 GW) and DPP 2023 cluster (195 withdrawn projects totaling 36.4 GW).

The first half of the year saw 283 GW exit. The second half was significantly larger at 450 GW. Only December exceeded 100 GW, but March (93 GW), April (87 GW), and July (87 GW) all came close. Unlike a one-time purge, this was a sustained, rolling cleanup, largely the product of staggered decision point deadlines hitting across different power markets at different times.

The full report breaks down regional withdrawal drivers — which ISOs drove each wave, cluster-by-cluster detail, and the impact of the ERAS fast-track program.

Included with purchase:

  • Starting Projects dataset (12,453 rows)
  • Ending Projects dataset (10,027 rows)
  • Added Projects dataset (2,140 rows)
  • Operational Projects dataset (408 rows)
  • GIA-Signed Projects dataset (2,722 rows)
  • Withdrawn Projects dataset (4,061 rows)
  • 46 charts with per-power-market breakdowns + printable PDF (no watermarks)
Get the Full Report

The Net Impact: A Shrinking Queue

The queue absorbed 733 GW in withdrawals, a record-shattering number. 481 GW of new capacity entered the queue in 2025, and another 50 GW of existing projects reached commercial operation. But additions couldn't keep pace with withdrawals, and the net result is a meaningfully leaner queue.

The U.S. interconnection queue shrank from 2,273 GW at the end of 2024 to roughly 1,971 GW at the end of 2025, a 13% reduction and the second consecutive year of contraction. That reversal is historically significant. From 2019 to 2023, queues grew 20-40% annually as cheap application fees and low barriers to entry created a classic tragedy of the commons: developers flooded the shared queue with speculative projects, degrading study timelines and grid access for everyone. FERC Order 2023 imposed the guardrails that the commons lacked, and the spray-and-pray era appears to be ending.

What's Left: Technology Shifts

Not all technologies were impacted equally. Natural gas was the only main technology to see meaningful growth, while all other technologies contracted (excluding some growth of the "Other" category, which covers a long-tail of less-common technologies like nuclear and pumped storage).

Natural gas was the standout technology to increase its presence in the queue. Nationally, gas capacity rose from 183 GW to 255 GW, a 39% increase. The growth was concentrated in the interior: MISO surged from 30.6 GW to 71.6 GW (+134%), SPP from 14.9 GW to 35.3 GW (+137%), and ERCOT from 29.4 GW to 43.1 GW (+47%).

Every other major technology contracted. Solar fell 21% from 921 GW to 731 GW, a massive absolute decline but also a sign that the remaining solar pipeline is more commercially serious. Standalone storage dropped 18%, offshore wind collapsed 46% as project economics continued to deteriorate, and onshore wind fell 13%. The hybrid category (solar-plus-storage combinations) declined 17%.

The full report includes regional technology breakdowns — which power markets grew vs contracted, and by how much.

Includes 46 charts (no watermarks), 6 project-level CSV datasets, and printable PDF.

Get the Full Report

The Long Wait: Queue Timelines

How long does it take to actually get through the queue? The answer in 2025 was: longer than ever. Projects that reached commercial operation last year waited a median of 5.9 years from queue entry, up from 5.1 years in 2024 and continuing a steady upward climb.

Queue reform was designed to fix this. But the projects completing in 2025 entered the queue around 2019 to 2020, before any of the current reforms took effect. Streamlined processes, cluster studies, and milestone-based screening may eventually reduce these timelines, but it will take years for those changes to show up in completion statistics. For now, the queue remains a long road.

The full report includes withdrawal timeline analysis — a leading indicator of whether queue reform is actually shortening study cycles.

Includes 46 charts (no watermarks), 6 project-level CSV datasets, and printable PDF.

Get the Full Report

What's Actually Getting Built

With so much attention on what's leaving the queue, it's worth asking: what's actually making it to the finish line? In 2025, at least 50 GW reached commercial operation across 400 projects, a tangible addition to the grid that gets lost in the headline withdrawal figures.

The most concrete indicator of near-term buildout is the pool of projects with signed Generator Interconnection Agreements (GIAs). These projects have cleared interconnection studies, negotiated contracts, and committed real capital. As of the end of 2025, roughly 488 GW of capacity holds signed GIAs, including about 19 GW in suspended status. ERCOT leads all markets with 133 GW, followed by the West at 86 GW, CAISO at 65 GW, MISO at 60 GW, and PJM at 53 GW.

This is the pipeline that matters most. While early-stage queue volumes are noisy and volatile, inflated by speculation and deflated by reform, GIA-backed projects represent the best signal we have of what's actually coming online. The fact that this pool grew even as the broader queue shrank suggests that the projects surviving the 2025 cleanup are further along in development, better capitalized, and more likely to reach operation. The queue is smaller, but the buildable pipeline is healthier than the top-line numbers imply.

Looking Ahead: The OBBBA Deadline

The next inflection point is already on the calendar. The One Big Beautiful Bill Act (OBBBA), signed into law in August 2025, set July 4, 2026 as the construction commencement deadline for solar and wind projects seeking federal tax credits — the investment tax credit (ITC) and production tax credit (PTC) that underpin the economics of most renewable energy development. The IRS followed with Notice 2025-42, which eliminated the 5% safe harbor that had previously allowed developers to qualify by ordering equipment alone. Projects must now demonstrate physical work of a significant nature at the project site by the deadline.

The full report quantifies OBBBA exposure — how many GW of solar, wind, and hybrid capacity are at risk of losing tax credits.

Includes 46 charts (no watermarks), 6 project-level CSV datasets, and printable PDF.

Get the Full Report

The queue that emerges from 2025 is fundamentally different from the one that entered it. It's smaller: 1,971 GW versus 2,273 GW a year earlier, a 13% reduction. Speculative projects have been culled. The remaining pipeline is weighted toward developers with signed agreements, secured sites, and real capital at risk. The path from queue to operation still takes nearly six years on average, and it's too early to tell whether reforms will meaningfully shorten that timeline. But the projects in line today are more likely to complete the journey. The central question for 2026 is whether the projects that remain can build fast enough to meet the deadlines now bearing down on them.

Methodology

Withdrawal dates: We use the reported withdrawal date when available. When not reported, we attribute the withdrawal to the month when we first detected the status change in our monthly snapshots.

Scope: The 733 GW headline figure counts projects that transitioned out of the Active or Suspended pool during 2025. Projects already withdrawn at the start of 2025 are excluded.

Comparison to 2024: Our 2024 retrospective reported 296 GW withdrawn, but that figure only included projects with explicitly recorded withdrawal dates. We estimate that captured between 50% and 67% of actual 2024 withdrawals, implying a true 2024 total of roughly 440 to 590 GW. This year's 733 GW figure uses a more comprehensive methodology based on our daily historical dataset, falling back to observed status transition dates when explicit withdrawal dates are not available. The methodological improvement means that a year-over-year comparison against our 2024 report is not strictly apples-to-apples, but even adjusting for the difference, 2025 withdrawals significantly exceeded 2024.

Data sourced from interconnection.fyi's database of queue filings across ISOs and utilities nationwide.

Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

Interconnection queue requests/projects in list format

All transmission grid interconnection queue requests/projects All distribution grid (DG) interconnection queue requests/projects Data center projects by state EIA860 planned and operational power plant projects

Insights

Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll blog posts

Other energy & climate tools

Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & ChartsBuy/Sell Surplus Transformers

Queue requests/projects by U.S. state


Queue requests/projects by Canadian province

Queue requests/projects by project type

GenerationLoadReplacementSurplusTransmissionUpgrade

Data Centers

All data center projects

By U.S. State

Interconnection queue requests/projects by transmission owner

Alberta Electric System OperatorAllegheny PowerAlliant Energy EastAlliant Energy WestAmeren IllinoisAmeren MissouriAmerican Electric PowerAmerican Municipal PowerAmerican Transmission CompanyAmerican Transmission SystemsArizona Public ServiceArkansas Electric Cooperative CorporationAssociated Electric CooperativeAvista UtilitiesBC HydroBaltimore Gas and ElectricBangor Hydro ElectricBasin Electric Power CooperativeBig Rivers Electric CorporationBlack Hills Cheyenne Light Fuel and Power TransmissionBlack Hills Colorado ElectricBlack Hills PowerBonneville Power AdministrationCedar Falls UtilitiesCentral Hudson Gas and ElectricCentral Maine PowerCentral Power Electric CooperativeChelan County Public Utility DistrictCity Utilities of Springfield MissouriCity Water, Light and PowerCity of Columbia, MissouriCity of Muscatine, IowaCleco HoldingsColorado River Storage Project TransmissionColorado Springs UtilitiesCommonwealth EdisonConsolidated EdisonConsumers EnergyCooperative EnergyCorn Belt Power CooperativeDCR TransmissionDairyland Power CooperativeDayton Power and LightDelmarva Power and LightDesertLinkDominion EnergyDominion Energy South CarolinaDuke EnergyDuke Energy CarolinasDuke Energy FloridaDuke Energy IndianaDuke Energy Ohio and KentuckyDuke Energy ProgressDuquesne Light CompanyEast Kentucky Power CooperativeEast River Electric Power CooperativeEast Texas Electric CooperativeEl Paso ElectricEmpire District Electric CompanyEntergyEntergy ArkansasEntergy LouisianaEntergy MississippiEntergy New OrleansEntergy TexasEssential PowerEvergyEvergy Missouri WestEversourceEwington Energy SystemsFirstEnergyFlorida Power and LightGeorgia TransmissionGrand River Dam AuthorityGrand River EnergyGrant County Public Utility DistrictGridLianceGridLiance WestGridUnityHenderson Municipal Power and LightHoosier EnergyHorizon West TransmissionHydro-QuébecIMEUISO New EnglandITC Great PlainsITC MidwestITC TransmissionIdaho Power CompanyImperial Irrigation DistrictIndependence Power and LightIndependent Electricity System OperatorIndianapolis Power and LightJacksonville Electric AuthorityJersey Central Power and LightKACYKansas City Board of Public UtilitiesKansas City Power and LightKansas Power PoolLS PowerLS Power Grid New YorkLafayette Utilities SystemLea County Electric CooperativeLincoln Electric SystemLong Island Power Authority
Los Angeles Department of Water and PowerLouisville Gas and Electric and Kentucky Utilities EnergyLoveland Area Projects TransmissionLower Yellowstone Rural Electric CooperativeMadison Gas and ElectricMaine Public ServiceManitoba HydroMetropolitan Edison CompanyMichigan Electric Transmission CompanyMichigan Public Power AgencyMid-Kansas Electric CompanyMidAmerican EnergyMidcontinent Independent System OperatorMidwest EnergyMinnesota Municipal Power AgencyMinnesota PowerMinnkota Power CooperativeMissouri River Energy ServicesMissouri Western Energy CorporationMontana-Dakota UtilitiesMunicipal Commission of BoonvilleNAEANB PowerNV EnergyNational GridNavajo-CrystalNebraska Public Power DistrictNew York Power AuthorityNew York State Electric and GasNew York TranscoNextEra Energy TransmissionNextEra Energy Transmission SouthwestNorthWestern EnergyNortheast UtilitiesNorthern Indiana Public ServiceNorthern States Power CompanyNorthwest Iowa Power CooperativeNorthwestern Wisconsin Electric CompanyNova Scotia PowerOhio Valley Electric CorporationOklahoma Gas and ElectricOld Dominion Electric CooperativeOmaha Public Power DistrictOrange and RocklandOrlando Utilities CommissionOtter Tail Power CompanyPECO Energy CompanyPJMPPL CorporationPacifiCorpPacific Gas and Electric CompanyPennsylvania Electric CompanyPeople's Electric CooperativePlatte River Power AuthorityPortland General ElectricPotomac Electric Power CompanyPrairie PowerPublic Service Company Of ColoradoPublic Service Company of New MexicoPublic Service Electric and GasPuget Sound EnergyRochester Gas and ElectricRochester Public UtilitiesRockland Electric CompanySacramento Municipal Utility DistrictSalt River ProjectSam Houston Electric CooperativeSan Diego Gas and ElectricSantee CooperSaskPowerSeminole Electric CooperativeSouth Mississippi Electric Power AssociationSouthern California EdisonSouthern CompanySouthern Illinois Power CooperativeSouthern Indiana Gas and Electric CompanySouthern Maryland Electric CooperativeSouthern Minnesota Municipal Power AgencySouthwestern Power AdministrationSouthwestern Public Service CompanySunflower Electric Power CorporationTacoma Public UtilitiesTampa Electric CompanyTennessee Valley AuthorityTransource MissouriTri-State Generation and Transmission AssociationTucson Electric PowerUnited Gas Improvement CompanyUnited Illuminating CompanyUpper Peninsula Power CompanyValley Electric AssociationVillage of ArcadeWAPA Sierra NevadaWAPA/BEPC/HCPD Integrated SystemWabash Valley Power AssociationWestar EnergyWestern Area Power AdministrationWestern Area Power Administration Desert Southwest RegionWestern Farmers Electric CooperativeWisconsin Electric Power CompanyWisconsin Public Service CorporationWolverine Power Supply CooperativeXcel Energy

© 2026 Interconnection.fyi. All rights reserved.

GridTracker by Interconnection.fyi

Full access to the data

See all the data

Find relevant dockets and filings

Track data center builds