🚀 New
GridTracker is the enterprise interconnection intelligence platform from Interconnection.fyiGridTracker for enterprise intelligenceGet more with GridTracker
Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

MISO Cluster: DPP-2018-APR West

Total Projects: 67

Active Projects: 18


Active Projects per county

Capacity by Generation Type

Network Upgrade Costs

(Per Megawatt)

Active Projects

Queue IDStatusCapacity (MW)Network Upgrade Cost ($/MW)Exact NumbersMost Recent Study Date
J1040Active250$150K - $300K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1045Active20<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1072Active150<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1084Active150<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1092Active100<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1124Active100<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1131Active100<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1132Active50<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1135Active50<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1164Active80$150K - $300K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1169Active50$150K - $300K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1174Active165<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1175Active165<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J953Active2<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J954Active1.4<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J963Active9<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J967Active150<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J982Active300<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021

Operational Projects

Queue IDStatusCapacity (MW)Network Upgrade Cost ($/MW)Exact NumbersMost Recent Study Date
J1050Operational225<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1181Operational200<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021

Withdrawn Projects

Queue IDStatusCapacity (MW)Network Upgrade Cost ($/MW)Exact NumbersMost Recent Study Date
J1001Withdrawn40$150K - $300K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1006Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1008Withdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1024Withdrawn200$150K - $300K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1032Withdrawn50$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1036Withdrawn130N/A👉

Get exact numbers with GridTracker

N/A
J1037Withdrawn15N/A👉

Get exact numbers with GridTracker

N/A
J1038Withdrawn32.5$300K - $750K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1041Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1054Withdrawn30$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1057Withdrawn125$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1061Withdrawn300<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1081Withdrawn300N/A👉

Get exact numbers with GridTracker

N/A
J1082Withdrawn400N/A👉

Get exact numbers with GridTracker

N/A
J1086Withdrawn120$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1098Withdrawn40>$1.5M / MW👉

Get exact numbers with GridTracker

2/16/2021
J1105Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1106Withdrawn414$300K - $750K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1108Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1109Withdrawn207$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1110Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

6/14/2021
J1114Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1122Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1128Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1140Withdrawn80$300K - $750K / MW👉

Get exact numbers with GridTracker

2/16/2021
J1143Withdrawn100$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1149Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1170Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1176Withdrawn145N/A👉

Get exact numbers with GridTracker

N/A
J1177Withdrawn300<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1179Withdrawn300<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J1185Withdrawn200N/A👉

Get exact numbers with GridTracker

N/A
J1187Withdrawn151.8$300K - $750K / MW👉

Get exact numbers with GridTracker

2/16/2021
J951Withdrawn80<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J952Withdrawn54$150K - $300K / MW👉

Get exact numbers with GridTracker

2/16/2021
J958Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J959Withdrawn150<$150K / MW👉

Get exact numbers with GridTracker

2/16/2021
J965Withdrawn150N/A👉

Get exact numbers with GridTracker

N/A
J966Withdrawn400$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J971Withdrawn250$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J975Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

6/14/2021
J977Withdrawn300$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J981Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

2/16/2021
J990Withdrawn150N/A👉

Get exact numbers with GridTracker

N/A
J997Withdrawn200<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020
J998Withdrawn50$150K - $300K / MW👉

Get exact numbers with GridTracker

3/18/2020
J999Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

3/18/2020

Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

Stay up to date via our email newsletter:

Interconnection queue requests/projects in list format

All transmission grid interconnection queue requests/projects All distribution grid (DG) interconnection queue requests/projects Data center projects by state EIA860 planned and operational power plant projects

Insights

Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll blog posts

Other energy & climate tools

Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & Charts

Queue requests/projects by U.S. state


Queue requests/projects by Canadian province

Queue requests/projects by project type

GenerationLoadReplacementSurplusTransmissionUpgrade

Data Centers

All data center projects

By U.S. State

Interconnection queue requests/projects by transmission owner

Alberta Electric System OperatorAllegheny PowerAlliant Energy EastAlliant Energy WestAmeren IllinoisAmeren MissouriAmerican Electric PowerAmerican Municipal PowerAmerican Transmission CompanyAmerican Transmission SystemsArizona Public ServiceArkansas Electric Cooperative CorporationAssociated Electric CooperativeAvista UtilitiesBC HydroBaltimore Gas and ElectricBangor Hydro ElectricBasin Electric Power CooperativeBig Rivers Electric CorporationBlack Hills Cheyenne Light Fuel and Power TransmissionBlack Hills Colorado ElectricBlack Hills PowerBonneville Power AdministrationCedar Falls UtilitiesCentral Hudson Gas and ElectricCentral Maine PowerCentral Power Electric CooperativeChelan County Public Utility DistrictCity Utilities of Springfield MissouriCity Water, Light and PowerCity of Columbia, MissouriCity of Muscatine, IowaCleco HoldingsColorado River Storage Project TransmissionColorado Springs UtilitiesCommonwealth EdisonConsolidated EdisonConsumers EnergyCooperative EnergyCorn Belt Power CooperativeDCR TransmissionDairyland Power CooperativeDayton Power and LightDelmarva Power and LightDesertLinkDominion EnergyDominion Energy South CarolinaDuke EnergyDuke Energy CarolinasDuke Energy FloridaDuke Energy IndianaDuke Energy Ohio and KentuckyDuke Energy ProgressDuquesne Light CompanyEast Kentucky Power CooperativeEast River Electric Power CooperativeEast Texas Electric CooperativeEl Paso ElectricEmpire District Electric CompanyEntergyEntergy ArkansasEntergy LouisianaEntergy MississippiEntergy New OrleansEntergy TexasEssential PowerEvergyEvergy Missouri WestEversourceEwington Energy SystemsFirstEnergyFlorida Power and LightGeorgia TransmissionGrand River Dam AuthorityGrand River EnergyGrant County Public Utility DistrictGridLianceGridLiance WestGridUnityHenderson Municipal Power and LightHoosier EnergyHorizon West TransmissionHydro-QuébecISO New EnglandITC Great PlainsITC MidwestITC TransmissionIdaho Power CompanyImperial Irrigation DistrictIndependence Power and LightIndependent Electricity System OperatorIndianapolis Power and LightJacksonville Electric AuthorityJersey Central Power and LightKACYKansas City Board of Public UtilitiesKansas City Power and LightKansas Power PoolLS PowerLS Power Grid New YorkLafayette Utilities SystemLea County Electric CooperativeLincoln Electric SystemLong Island Power Authority
Los Angeles Department of Water and PowerLouisville Gas and Electric and Kentucky Utilities EnergyLoveland Area Projects TransmissionLower Yellowstone Rural Electric CooperativeMadison Gas and ElectricMaine Public ServiceManitoba HydroMetropolitan Edison CompanyMichigan Electric Transmission CompanyMichigan Public Power AgencyMid-Kansas Electric CompanyMidAmerican EnergyMidcontinent Independent System OperatorMidwest EnergyMinnesota Municipal Power AgencyMinnesota PowerMinnkota Power CooperativeMissouri River Energy ServicesMissouri Western Energy CorporationMontana-Dakota UtilitiesMunicipal Commission of BoonvilleNAEANB PowerNV EnergyNational GridNavajo-CrystalNebraska Public Power DistrictNew York Power AuthorityNew York State Electric and GasNew York TranscoNextEra Energy TransmissionNextEra Energy Transmission SouthwestNorthWestern EnergyNortheast UtilitiesNorthern Indiana Public ServiceNorthern States Power CompanyNorthwest Iowa Power CooperativeNorthwestern Wisconsin Electric CompanyNova Scotia PowerOhio Valley Electric CorporationOklahoma Gas and ElectricOld Dominion Electric CooperativeOmaha Public Power DistrictOrange and RocklandOrlando Utilities CommissionOtter Tail Power CompanyPECO Energy CompanyPJMPPL CorporationPacifiCorpPacific Gas and Electric CompanyPennsylvania Electric CompanyPeople's Electric CooperativePlatte River Power AuthorityPortland General ElectricPotomac Electric Power CompanyPrairie PowerPublic Service Company Of ColoradoPublic Service Company of New MexicoPublic Service Electric and GasPuget Sound EnergyRochester Gas and ElectricRochester Public UtilitiesRockland Electric CompanySacramento Municipal Utility DistrictSalt River ProjectSan Diego Gas and ElectricSantee CooperSaskPowerSeminole Electric CooperativeSouth Mississippi Electric Power AssociationSouthern California EdisonSouthern CompanySouthern Illinois Power CooperativeSouthern Indiana Gas and Electric CompanySouthern Maryland Electric CooperativeSouthern Minnesota Municipal Power AgencySouthwestern Power AdministrationSouthwestern Public Service CompanySunflower Electric Power CorporationTacoma Public UtilitiesTampa Electric CompanyTennessee Valley AuthorityTransource MissouriTri-State Generation and Transmission AssociationTucson Electric PowerUnited Gas Improvement CompanyUnited Illuminating CompanyUpper Peninsula Power CompanyValley Electric AssociationVillage of ArcadeVillage of IlionWAPA Sierra NevadaWAPA/BEPC/HCPD Integrated SystemWabash Valley Power AssociationWestar EnergyWestern Area Power AdministrationWestern Area Power Administration Desert Southwest RegionWestern Farmers Electric CooperativeWisconsin Electric Power CompanyWisconsin Public Service CorporationWolverine Power Supply CooperativeXcel Energy

© 2026 Interconnection.fyi. All rights reserved.

GridTracker by Interconnection.fyi

Full access to the data

See all the data

Find relevant dockets and filings

Track data center builds