PJM Cluster: TC1

Total Projects: 315

Active Projects: 83


Active Projects per county

Capacity by Generation Type

Network Upgrade Costs

(Per Megawatt)

Active Projects

Queue IDProject NameStatusCapacity (MW)Network Upgrade Cost ($/MW)Exact NumbersMost Recent Study Date

AE1-092

Fountain Point SolarActive206.55<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE1-114

Leaf River WindActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-156

Yadkins Energy CenterActive100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-185

Pigeon Run Solar and StorageActive60<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-223

Bright Stalk Generating FacilityActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-261

Black Diamond SolarActive299<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-283

Gladys SolarActive53$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-291

Hillandale SolarActive102$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-308

Madison SolarActive100$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-341

Plano Skies Energy CenterActive150$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-030

Plano Skies Energy CenterActive100$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-123

CVOW 1, OSS 1 - T1L11Active833$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-124

CVOW 2, OSS 2 – T2G07Active836$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-125

CVOW 3, OSS 3 – T3G15Active820$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-128

Chesterfield CT Units 1 and 2Active569<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-161

Decatur Battery StorageActive50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-176

Three Lakes SolarActive300$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-204

Vermilion Grove WindActive255<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-233

Fleming SolarActive188.5<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-238

South OrchardActive50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-280

South Dixon SolarActive200<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-294

Amelia Energy FacilityActive41$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-296

Gipper Wind FarmActive190.89<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-025

Missouri Avenue Battery Storage ProjectActive20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-041

Steward Creek SolarActive300$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-042

Randolph SolarActive500$750K - $1M / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-050

Maple Hill-Fiddlers 1 SP (Bear Rock)Active50$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-068

Rosegold SolarActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-081

Currituck SolarActive80<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-095

Kankakee SolarActive144<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-111

Goldfinch SolarActive250<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-115

Amelia Energy FacilityActive25$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-120

Cerulean Solar and Mulberry BESSActive62$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-126

Juliet EnergyActive12<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-142

Otter Creek SolarActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-143

Osagrove Flats SolarActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-177

Teays River Wind FarmActive200<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-182

South Dixon SolarActive300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-199

Steward Creek SolarActive100$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-200

Steward Creek SolarActive200$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-222

Courthouse SolarActive167$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-225

Bright Stalk Generating FacilityActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-226

Top Crop Generating FacilityActive50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-296

CL- Belsena SolarActive20<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-299

Jarratt Energy Facility 2Active18<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-319

Top Crop Generating FacilityActive50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-349

Pleasant Grove SolarActive300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-350

Grand Marsh SolarActive100$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-376

Timber Road II WFActive50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-388

Prairie Creek WindActive200<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-396

Cass County SolarActive200$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-404

Pigeon Run Solar and StorageActive0N/A👉

Get exact numbers with GridTracker

9/18/2025

AF2-441

Riverbank EnergyActive200<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-021

Amelia Energy FacilityActive20$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-090

Black Moshannon SolarActive95<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-105

Clover Creek SolarActive90$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-109

Decatur Battery StorageActive25<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-118

Burr Oak SolarActive300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-124

Wild Rose Solar ProjectActive90$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-127

Red Maple SolarActive95.1<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-135

Moon Corner SolarActive60$750K - $1M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-153

Brunswick Battery StorageActive75<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-226

Dolphin SolarActive450<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-285

Quarter Horse SolarActive125$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-320

Stonecrop SolarActive82<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-341

Summer Shade SolarActive106<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-342

Staunton SolarActive36$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-354

Exie SolarActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-374

Dawson SolarActive300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-377

Black Moshannon SolarActive20$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-378

Black Moshannon SolarActive20$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-410

Butterfly MeadowsActive300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-411

Butterfly MeadowsActive100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-433

Prairie Creek Wind Phase 2Active100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-436

Bluestem SolarActive125<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-447

Bluestem SolarActive55<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-460

Black Diamond SolarActive30$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-462

Gipper Solar FarmActive255<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-471

BarrelheadActive54$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-483

Fourth QuarterActive500<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-536

Cerulean Solar and Mulberry BESSActive75$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-548

French Creek Solar and BESSActive150<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-553

Beacon SolarActive260<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

Withdrawn Projects

Queue IDProject NameStatusCapacity (MW)Network Upgrade Cost ($/MW)Exact NumbersMost Recent Study Date

AE1-070

Withdrawn135$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE1-148

Antlers Road SolarWithdrawn90$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE1-172

Livingston WindWithdrawn255$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-053

Withdrawn20$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-107

Withdrawn90<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-123

Withdrawn800.1$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-124

Withdrawn800.1$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-130

Withdrawn800<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-138

Withdrawn260<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-147

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-173

Blooming Grove Solar Energy CenterWithdrawn50<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-187

Shockoe Solar FarmWithdrawn60$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-210

Withdrawn90$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-250

Withdrawn82.5$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-270

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-275

Withdrawn90$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-292

Withdrawn127$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AE2-313

Withdrawn314$750K - $1M / MW👉

Get exact numbers with GridTracker

12/18/2024

AE2-321

McHenry County Solar ProjectWithdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AE2-325

Southwest Michigan Energy CenterWithdrawn52.2<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-048

Withdrawn52.2$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-088

Grain Belt TransmissionWithdrawn1000<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF1-099

Withdrawn126.5$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-100

Withdrawn250$750K - $1M / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-116

Withdrawn120<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF1-142

Withdrawn202.4$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-152

Withdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-200

Withdrawn2100<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF1-201

Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-221

Withdrawn180$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-240

AR-PIERCEWithdrawn15.75<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF1-252

Withdrawn62.4<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-253

Withdrawn43.2<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-266

Withdrawn74.5$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-270

Withdrawn50<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF1-276

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-277

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-278

Withdrawn80$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-281

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-293

Withdrawn127.86$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-301

Withdrawn117$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-306

Withdrawn197.2$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-314

Withdrawn212$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF1-318

Withdrawn299.97$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF1-323

Withdrawn55$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-008

Grain Belt TransmissionWithdrawn2000<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF2-010

Union SolarWithdrawn77$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-016

Withdrawn240$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-021

Withdrawn20$1M - $1.5M / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-034

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-035

Anna River SolarWithdrawn72$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-037

Withdrawn94$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-046

Murphy SolarWithdrawn126$1M - $1.5M / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-047

Withdrawn150$750K - $1M / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-056

Withdrawn50>$1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-063

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-065

Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-069

Lone Tree Wind FarmWithdrawn8.4$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-070

Withdrawn18.15<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-080

Brookfield Pitt SolarWithdrawn70$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-096

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-128

Withdrawn79.5$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-164

Withdrawn80$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-171

Withdrawn150$750K - $1M / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-173

Esker Solar ParkWithdrawn140<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-176

Withdrawn60$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-183

Withdrawn80$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-193

Withdrawn440$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-194

Withdrawn440$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-201

Withdrawn199$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-209

Withdrawn140$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-263

Withdrawn98<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-297

Sedge Hill SolarWithdrawn80$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-302

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-307

Flat Top SolarWithdrawn64.2$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-321

Withdrawn148>$1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-324

Withdrawn75$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-329

Withdrawn42.2$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-335

Royerton Solar and StorageWithdrawn100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-348

Withdrawn250$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-351

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-355

Withdrawn225<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-358

Choptank Solar and StorageWithdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-365

Hart SolarWithdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-370

Royerton Solar and StorageWithdrawn20<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-381

Withdrawn60$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-391

Withdrawn120<$150K / MW👉

Get exact numbers with GridTracker

N/A

AF2-392

Bison Meadows Wind ProjectWithdrawn199$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-393

Withdrawn60$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-394

Withdrawn40$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-397

Withdrawn130$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-403

Shockoe Storage / Shockoe DP-Chatham 69 kVWithdrawn8$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AF2-406

Withdrawn75$750K - $1M / MW👉

Get exact numbers with GridTracker

5/16/2024

AF2-407

Liberty II StorageWithdrawn300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AF2-412

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-005

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-008

Bells SolarWithdrawn126$1M - $1.5M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-011

Withdrawn160$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-019

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-022

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-030

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-051

Withdrawn20<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-060

Withdrawn174.8$750K - $1M / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-061

Withdrawn109.3$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-070

Wood Duck 100 MWWithdrawn45$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-071

Wood Duck 100 MWWithdrawn55$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-075

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-082

NC1 Ahoskie Central Solar ProjectWithdrawn20$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-083

Withdrawn20$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-098

Finneywood SolarWithdrawn107$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-106

Oak SolarWithdrawn23$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-119

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-120

Withdrawn118.6$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-121

Withdrawn294.7$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-123

Withdrawn65<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-133

Withdrawn128$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-134

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-146

Merry Point SolarWithdrawn30$1M - $1.5M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-147

Merry Point SolarWithdrawn70$750K - $1M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-151

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-154

Ladysmith Battery StorageWithdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-160

Withdrawn75<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-166

NW-Rocky Ford SolarWithdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-167

NW-Rocky Ford SolarWithdrawn15$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-168

NW-Rocky Ford SolarWithdrawn15$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-169

Withdrawn15$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-170

Withdrawn10$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-174

Withdrawn20<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-178

Withdrawn500$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-179

Withdrawn50$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-180

Withdrawn16.4$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-181

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-184

Withdrawn175.06$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-185

Withdrawn48.91$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-194

Withdrawn79$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-195

Withdrawn150<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-196

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-199

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-219

Withdrawn75$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-224

Withdrawn210<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-225

Withdrawn346$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-236

Ramble WindWithdrawn180<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-272

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-273

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-274

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-277

Withdrawn40$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-278

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-279

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-284

Withdrawn70$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-288

Withdrawn150<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-289

Withdrawn53.41<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-297

Blue River StorageWithdrawn300<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-298

Withdrawn500$150K - $300K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-305

Withdrawn63$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-306

Withdrawn65<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-308

Withdrawn19.9$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-319

Withdrawn65$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-321

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

5/24/2024

AG1-323

Bellefontaine PV and BESS ProjectWithdrawn40<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-343

Withdrawn62.5$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-346

Withdrawn20<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-353

Withdrawn98$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-359

Withdrawn127.5$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-364

Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-367

Esker Solar Park IIWithdrawn100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-371

Withdrawn30$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-373

Withdrawn10>$1.5M / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-375

Blackford County SolarWithdrawn100<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-379

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-384

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-392

Withdrawn30$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-392A

Withdrawn30<$150K / MW👉

Get exact numbers with GridTracker

N/A

AG1-392B

Withdrawn15<$150K / MW👉

Get exact numbers with GridTracker

N/A

AG1-392C

Withdrawn15<$150K / MW👉

Get exact numbers with GridTracker

N/A

AG1-393

DW-Lew Jones SolarWithdrawn20<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-394

SH-Mehrrin SolarWithdrawn14.2<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-399

Withdrawn300$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-400

Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-402

Withdrawn150$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-404

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-405

Sunflower PrairieWithdrawn57<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-406

Sunflower PrairieWithdrawn22$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-412

Withdrawn200$750K - $1M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-421

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-422

Withdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-423

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-424

Withdrawn100$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-425

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-426

Withdrawn17<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-427

Withdrawn118.56$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-428

Withdrawn46.8$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-432

Withdrawn200$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-434

Withdrawn175$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-435

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-437

Withdrawn100$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-438

Withdrawn100$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-439

Withdrawn250$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-440

Withdrawn75<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-441

Withdrawn75<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-442

Withdrawn35$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-443

Withdrawn35$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-444

Withdrawn80$750K - $1M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-445

Withdrawn26<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-446

Withdrawn26<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-449

Withdrawn122$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-450

Choptank Solar and StorageWithdrawn25$300K - $750K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-451

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-453

Withdrawn140<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-454

Withdrawn50<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-456

Withdrawn30<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-473

Withdrawn53.9$1M - $1.5M / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-488

Withdrawn70$300K - $750K / MW👉

Get exact numbers with GridTracker

5/24/2024

AG1-494

Mainspring GridWithdrawn50$150K - $300K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-497

Withdrawn120<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-502

Withdrawn80$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-503

Withdrawn20$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-505

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-506

Withdrawn150$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-522

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-523

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-524

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-525

Withdrawn300$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-526

Garrard SolarWithdrawn222<$150K / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-531

Withdrawn54$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-537

Withdrawn75$300K - $750K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-538

Withdrawn75<$150K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-539

Withdrawn75$150K - $300K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-547

Withdrawn50$300K - $750K / MW👉

Get exact numbers with GridTracker

5/16/2024

AG1-549

Withdrawn100<$150K / MW👉

Get exact numbers with GridTracker

12/18/2024

AG1-551

Parnell SolarWithdrawn19.99$750K - $1M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-552

Ray SolarWithdrawn18$1M - $1.5M / MW👉

Get exact numbers with GridTracker

9/18/2025

AG1-556

Withdrawn100$1M - $1.5M / MW👉

Get exact numbers with GridTracker

5/16/2024

Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

Stay up to date via our email newsletter:

Interconnection queue requests/projects in list format

All transmission grid interconnection queue requests/projects All distribution grid (DG) interconnection queue requests/projects Data center projects by state EIA860 planned and operational power plant projects

Insights

Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll insights

Other energy & climate tools

Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & ChartsBuy/Sell Surplus Transformers

Queue requests/projects by U.S. state


Queue requests/projects by Canadian province

Queue requests/projects by project type

GenerationLoadReplacementSurplusTransmissionUpgrade

Data Centers

All data center projects

By U.S. State

Interconnection queue requests/projects by transmission owner

Alberta Electric System OperatorAllegheny PowerAlliant Energy EastAlliant Energy WestAmeren IllinoisAmeren MissouriAmerican Electric PowerAmerican Municipal PowerAmerican Transmission CompanyAmerican Transmission SystemsArizona Public ServiceArkansas Electric Cooperative CorporationAssociated Electric CooperativeAvista UtilitiesBC HydroBaltimore Gas and ElectricBangor Hydro ElectricBasin Electric Power CooperativeBig Rivers Electric CorporationBlack Hills Cheyenne Light Fuel and Power TransmissionBlack Hills Colorado ElectricBlack Hills PowerBonneville Power AdministrationCedar Falls UtilitiesCentral Hudson Gas and ElectricCentral Maine PowerCentral Power Electric CooperativeChelan County Public Utility DistrictCity Utilities of Springfield MissouriCity Water, Light and PowerCity of Columbia, MissouriCity of Muscatine, IowaCleco HoldingsColorado River Storage Project TransmissionColorado Springs UtilitiesCommonwealth EdisonConsolidated EdisonConsumers EnergyCooperative EnergyCorn Belt Power CooperativeDCR TransmissionDairyland Power CooperativeDayton Power and LightDelmarva Power and LightDesertLinkDominion EnergyDominion Energy South CarolinaDuke EnergyDuke Energy CarolinasDuke Energy FloridaDuke Energy IndianaDuke Energy Ohio and KentuckyDuke Energy ProgressDuquesne Light CompanyEast Kentucky Power CooperativeEast River Electric Power CooperativeEast Texas Electric CooperativeEl Paso ElectricEmpire District Electric CompanyEntergyEntergy ArkansasEntergy LouisianaEntergy MississippiEntergy New OrleansEntergy TexasEssential PowerEvergyEvergy Missouri WestEversourceEwington Energy SystemsFarmington Electric Utility SystemFirstEnergyFlorida Power and LightGeorgia TransmissionGrand River Dam AuthorityGrand River EnergyGrant County Public Utility DistrictGridLianceGridLiance WestGridUnityHenderson Municipal Power and LightHoosier EnergyHorizon West TransmissionHydro-QuébecIMEUISO New EnglandITC Great PlainsITC MidwestITC TransmissionIdaho Power CompanyImperial Irrigation DistrictIndependence Power and LightIndependent Electricity System OperatorIndianapolis Power and LightJacksonville Electric AuthorityJersey Central Power and LightKACYKansas City Board of Public UtilitiesKansas City Power and LightKansas Power PoolLS PowerLS Power Grid New YorkLafayette Utilities SystemLea County Electric CooperativeLincoln Electric System
Long Island Power AuthorityLos Angeles Department of Water and PowerLouisville Gas and Electric and Kentucky Utilities EnergyLoveland Area Projects TransmissionLower Yellowstone Rural Electric CooperativeMadison Gas and ElectricMaine Public ServiceManitoba HydroMetropolitan Edison CompanyMichigan Electric Transmission CompanyMichigan Public Power AgencyMid-Kansas Electric CompanyMidAmerican EnergyMidcontinent Independent System OperatorMidwest EnergyMinnesota Municipal Power AgencyMinnesota PowerMinnkota Power CooperativeMissouri River Energy ServicesMissouri Western Energy CorporationMontana-Dakota UtilitiesMunicipal Commission of BoonvilleNAEANB PowerNV EnergyNational GridNavajo-CrystalNebraska Public Power DistrictNew York Power AuthorityNew York State Electric and GasNew York TranscoNextEra Energy TransmissionNextEra Energy Transmission SouthwestNorthWestern EnergyNortheast UtilitiesNorthern Indiana Public ServiceNorthern States Power CompanyNorthwest Iowa Power CooperativeNorthwestern Wisconsin Electric CompanyNova Scotia PowerOhio Valley Electric CorporationOklahoma Gas and ElectricOld Dominion Electric CooperativeOmaha Public Power DistrictOrange and RocklandOrlando Utilities CommissionOtter Tail Power CompanyPECO Energy CompanyPJMPPL CorporationPacifiCorpPacific Gas and Electric CompanyPennsylvania Electric CompanyPeople's Electric CooperativePlatte River Power AuthorityPortland General ElectricPotomac Electric Power CompanyPrairie PowerPublic Service Company Of ColoradoPublic Service Company of New MexicoPublic Service Electric and GasPuget Sound EnergyRochester Gas and ElectricRochester Public UtilitiesRockland Electric CompanySacramento Municipal Utility DistrictSalt River ProjectSam Houston Electric CooperativeSan Diego Gas and ElectricSantee CooperSaskPowerSeminole Electric CooperativeSouth Mississippi Electric Power AssociationSouthern California EdisonSouthern CompanySouthern Illinois Power CooperativeSouthern Indiana Gas and Electric CompanySouthern Maryland Electric CooperativeSouthern Minnesota Municipal Power AgencySouthwestern Power AdministrationSouthwestern Public Service CompanySunflower Electric Power CorporationTacoma Public UtilitiesTampa Electric CompanyTennessee Valley AuthorityTransource MissouriTri-State Generation and Transmission AssociationTucson Electric PowerUnited Gas Improvement CompanyUnited Illuminating CompanyUpper Peninsula Power CompanyValley Electric AssociationVillage of ArcadeWAPA Sierra NevadaWAPA/BEPC/HCPD Integrated SystemWabash Valley Power AssociationWestar EnergyWestern Area Power AdministrationWestern Area Power Administration Desert Southwest RegionWestern Farmers Electric CooperativeWisconsin Electric Power CompanyWisconsin Public Service CorporationWolverine Power Supply CooperativeXcel Energy

© 2026 Interconnection.fyi. All rights reserved.

GridTracker by Interconnection.fyi

Full access to the data

See all the data

Find relevant dockets and filings

Track data center builds